Project-specific working schedules

Hello.

Is there a way to make the estimating process take account of project-specific priorities?

An example:

I have 3 projects, Project X, Project Y, and Project Z.

I'm going to spend 50% of my time on Project X, 25% of my time on project Y, and 25% of my time on project Z.

At the moment, I believe that Fogbugz assumes equal waiting of my time between each project. Is that correct?
Nick Pierpoint Send private email
Thursday, October 2, 2008
 
 
FogBugz assumes you are working 100% on whichever project you are looking at on EBS.

If those are your weightings, just take your EBS graph, and figure out how many "work days" it is suggesting... Then just divid it by your "time percentage" on that project to figure effectively when you will finish it.
Michael H. Pryor Send private email
Thursday, October 2, 2008
 
 
Thanks Michael.

Must admit though, it seems a little clunky. I suppose the assumed way of working is to complete one project then move on to the next. (I wish!)
Nick Pierpoint Send private email
Friday, October 3, 2008
 
 