Original and current estimates

Hi,

When I open a case I enter the original estimate, for example 1h. I start working and when I resolve the case, I might have been pessimistic with the original estimate because I realize that I have only worked on the case for 30 minutes. Should I also enter a current estimate equal to the elapsed time? If I don't, I see that I have more work to do. I stop seeing that only if I close the case and goes out of my filter results. Also, if I don't, will the EBS algorithm produce accurate reports?

Thank you,
Petros
Petros Amiridis Send private email
Thursday, September 20, 2007
 
 
Hi Petros,

Please check out the discussion at http://our.fogbugz.com/default.asp?fogbugz.4.18421.7 and see if that answers your questions. 

EBS will take into account your tendencies over time.  If you consistently overestimate, then it will learn that about you, and adjust the release times that it predicts accordingly.
Eric Nehrlich Send private email
Thursday, September 20, 2007
 
 
Great! I understood that I should not "correct" the current estimate to the final elapsed time when I close a case.

Thanks,
Petros
Petros Amiridis Send private email
Friday, September 21, 2007
 
 

This topic is archived. No further replies will be accepted.

Other recent topics Other recent topics
 
Powered by FogBugz Bug Tracking and Evidence-Based Scheduling.